TLO Beam Replacement

Site:

Christmas Creek

Service:

SMP

Client:

FMG

Project Executive Summary Fact Sheet

Scope

Replace Structural Beams in TLO

  • Set up areas with tempory handrails and boarding for SIMOPS
  • Remove Old beams
  • Remove and weld on new cleats as required
  • Complete NDT as per QA management plan
  • Install new beams and complete QA documentation for sign off
  • Touch up painting
  • Install grating and sercure
  • Remove tempory handrails and boarding
  • All completed with in time and no incidents